Published : 01-07-2019
Yasar Abedeen, director of the General Company for Engineering Studies and Consulting, run by the Syrian Ministry of Public Works and Housing, said the company has been tasked with devising reconstruction plans for Yarmouk Camp, in Damascus, and surrounding areas.
Speaking with state-run media, Abedeen said Yarmouk Camp comes on top of the newly-signed contracts. Reconstruction is slated to be carried out along three phases and to last for 135 days.
The first phase encompasses an overall assessment of the organizational plan for 2013 and of the damage inflicted by the warfare. Airborne imagery has been implemented to that end.
As part of the second phase, proposals will be put forth in cooperation with the follow-up committee in order to reach a final decision regarding the opted-for vision.
The last phase includes a detailed outline of the final plan for the reconstruction of the camp.
Yasar Abedeen, director of the General Company for Engineering Studies and Consulting, run by the Syrian Ministry of Public Works and Housing, said the company has been tasked with devising reconstruction plans for Yarmouk Camp, in Damascus, and surrounding areas.
Speaking with state-run media, Abedeen said Yarmouk Camp comes on top of the newly-signed contracts. Reconstruction is slated to be carried out along three phases and to last for 135 days.
The first phase encompasses an overall assessment of the organizational plan for 2013 and of the damage inflicted by the warfare. Airborne imagery has been implemented to that end.
As part of the second phase, proposals will be put forth in cooperation with the follow-up committee in order to reach a final decision regarding the opted-for vision.
The last phase includes a detailed outline of the final plan for the reconstruction of the camp.